Water Mains upgrade underway in Fossa
Uisce Éireann has started works in Crohane and Dromkerry to replace 1.8 kilometres of old water mains along the L-11012 Gortacollopa, from the junction of the N72 at Crohane
. The ageing pipes have been prone to bursts, and the upgrade aims to improve the reliability of supply and reduce leakage.
The project, being delivered by Ward and Burke Construction Ltd on behalf of Uisce Éireann, is expected to finish by the end of August 2025. Some short-term water interruptions may occur, with at least 48 hours’ notice given to customers before any planned disruption.
Uisce Éireann says the work will help secure a more reliable water supply for the local community and reduce water loss.
Project Details
Location: Crohane and Dromkerry, Fossa
Length of mains replaced: 1.8 km
Expected completion: End of August 2025
Contractor: Ward and Burke Construction Ltd
News
Carrig Cup gathering honours Mike Gaine
News
Local talent Orna Cleary O’Shea takes lead role in ‘All Shook Up’
Residents of Killarney will recognise many familiar faces when Killarney Musical Society stages All Shook Up on February 10, 11 and 12 in the Gleneagle Arena. The society is marking […]