Roadworks not expected to finish until March
Frustration is mounting in Killarney over ongoing delays to the active travel and road resurfacing project on Park Road.
The works, which were originally scheduled to be completed before Christmas, are now running six weeks behind schedule.
Contractors have indicted the project could take another three weeks to finish.
The one-way system currently operating is expected to finish today.
Part of the delay has been attributed to additional, unplanned works to replace a water main along Park Road.
There is a serious impact on traffic flow in the town with heavy congestion along Countess Road.
Mayor of Killarney Cllr Martin Grady said it is unacceptable for a project of this scale to run so far over schedule, given the strain it is placing on residents, commuters and families during peak times.
However, following discussions with the contractor, he has been assured that the project is now in its final stages, with full completion expected within the next three to four weeks.